TUSTIN ZONE 3 WATER REPLACEMENT PROJECT, TUSTIN, CALIFORNIA

This project consists of the replacement of the existing Zone 3, 6″ water distribution main in E. Skyline Drive, with a new 8″ ductile iron pipeline. The project site is located on the border of the City of Tustin’s Zone 2 and Zone 3 service areas, and the Southern California Water Company’s service area. The project limits were from Beverly Glen Drive to Racquet Hill. The improvements include abandonment of the existing 6″ main and construction of a new 8″ water main with new fire hydrant and water meter connections. Temporary water service was maintained during construction. There were also interconnections to the existing Zone 3 facilities in Beverly Glen Drive and Racquet Hill, and an interconnection to Southern California Water facilities at the intersection of Racquet Hill.